St. Mary River Irrigation District 

The following is a complete list of all projects included in the St. Mary River Irrigation District (SMRID) under this program. There are 29 pipeline modernization projects, one structure rehabilitation and one shared reservoir project.

Note that in August of 2022, SMRID amalgamated with the Taber Irrigation District (TID). For clarity, the TID projects are included below and identified with a tag in parentheses after the project name. Some of the projects are being phased over multiple years. The total approved budget for the combined SMRID and TID program is $205,586,000 M.

Pipeline Projects

All pipeline modernization projects are scheduled for completion by 2027/2028. The proposed schedule of projects is detailed in the tables below. Approximately 210 km of canal will be replaced with buried PVC pipelines, which will result in significant water savings and efficiency gains through reduced seepage, evaporation and the elimination of tail-out losses. Approximately 57,500 ac of farmland are served by these systems.

PVC pipelines have an expected lifespan in excess of 80 years and the assets will be incorporated into the District’s long-term Asset Management plan.

The remaining construction is being phased from 2024-2025 to 2027-2028 with projects grouped by area (West SMRID, Middle and East). Where possible, the District will aggregate smaller projects into larger bid packages as volume discounts can sometimes be achieved by tendering construction projects in this fashion.

Construction is being tendered to local contractors through a prequalification process prior to the bid packages sent out.

Accounting for tailout, evaporation and seepage, it is estimated that the district will save on average 31,500 ac-ft per year from these projects.

Table 1. Completed SMRID Modernization Projects (2020/2021 to 2023/2024)

Project Name

Project Description

Cost Estimate

Cameron Lateral Pipeline

Pipeline 

$7,000,000

Sauder Chute Replacement

Structure Rehabilitation

$13,000,000

Eight Mile Lateral

Pipeline 

$3,100,000

West Medicine Hat 2

Pipeline 

$18,500,000

Whoop‐Up Lateral

Pipeline 

$5,850,000

Main Canal 7

Pipeline 

$2,340,000

Jail Road Lateral

Pipeline 

$3,276,000

Chin 2‐2

Pipeline 

$1,950,000

Chin 4/Chin 5

Pipeline 

$5,148,000

Bow Island Lateral 10

Pipeline 

$19,656,000

North Burdett Lateral 5

Pipeline 

$2,340,000

Sauder Reservoir Lateral 34

Pipeline 

$4,170,000

Bow Island Lateral 22

Pipeline 

$5,525,000

West Medicine Hat Lateral 31

Pipeline 

$5,525,000

West Medicine Hat Lateral 38

Pipeline 

$2,600,000

South Medicine Hat Lateral 3

Pipeline 

$5,850,000

M Big Bend Pipeline (TID)

Pipeline 

$6,016,000

North Fincastle West Pipeline (TID)

Pipeline 

$3,200,000

Table 2. Current SMRID Modernization Projects (2024/2025 Completion)

Project Name

Project Description

Cost Estimate

Yellow Lake Laterals 8 – 10

Pipeline 

$24,570,000

Cameron Extension 1-7 Pipeline

Pipeline

$9,750,000

1B Barnwell (TID)

Pipeline

$1,007,000

Horsefly Lateral 6

Pipeline

$975,000

 

Table 3. 2025/2026 SMRID Modernization Projects

Project Name

Project Description

Cost Estimate

North lateral ‐ Sec 13‐10‐21

Pipeline 

$650,000

West Medicine Hat 10/13 (phase 1)

Pipeline 

$7,312,500

Chin 2 Ext. 1

Pipeline

$650,000

Bow Island 31A

Pipeline

$1,300,000

Bow Island 32

Pipeline

$1,300,000

Table 4. 2026/2027 SMRID Modernization Projects

Project Name

Project Description

Cost Estimate

SMRID Grassy Lake Project

Pipeline / canal rehabilitation

$3,100,000

West Medicine Hat 10/13 (phase 2)

Pipeline 

$7,312,500

Big Bend Main Pipeline, phase 1 (TID)

Pipeline 

$15,331,500

 

Table 5. 2027/2028 SMRID Modernization Projects

Project Name

Project Description

Cost Estimate

Big Bend Main Pipeline, phase 2 (TID)

Pipeline 

$15,331,500

North Lateral – Baczuk Pipeline

Pipeline

$1,950,000

 

 

Total Cost of all SMRID modernization projects = $205,586,000 M

AIM West
AIM Central
AIM East

Sauder Chute Spillway and Modernization Project (Completed Spring 2022)

Overview

The Sauder project replaced an existing cast-in-place chute spillway system that was constructed in 1954 and was in a deteriorated state. The spillway was enlarged to better accommodate larger flood events and a new automated spillway gate and control system was added. The enlarged gate system and controls enhance SMRID’s water management and reduces spill by having improved levels of control at higher water levels.


Sauder Reservoir is located approximately 21 km southwest of the City of Medicine Hat and is an important off-stream storage reservoir for the eastern part of the SMRID. The primary service spillway for the reservoir is the Sauder Chute, located on the left abutment of the Sauder Main Dam. The chute was constructed with the Main Dam in 1954 and the inlet channel was improved in 1981. A bridge carries Township Road 121A over the inlet channel, which was enlarged as part of the project, requiring the bridge to also be replaced.

Sauder Chute Spillway and Modernization Project Site Overview
Site Overview

Flow into the chute is controlled at the head of the inlet channel by the inlet structure equipped with an overshot gate to control flow down Sauder Chute.  The original design capacity of the chute was 32.3 m3/s at the reservoir design flood elevation of 804.65 m. The proposed replacement spillway is a cast-in-place chute structure with a conventional USBR Type Ill stilling basin.

Based on the recommendations of the Regional Storm Water Management Master Plan (2014) and a 2020 Dam Safety Review, the replacement structure was designed for a higher capacity of 75 m3/s to allow passage of flood flows from the SMRID Main Canal upstream. The higher capacity required a wider replacement structure as well as an expansion of the inlet channel and the grouted rip-rap overflow weir was replaced with an undershot gate to achieve a better level of water management control during flood events.

Schedule

This project was completed in the 2021/2022 construction season. 

Cost Estimate

The total cost of all components of the replacement project was estimated at $13 M and came in slightly underbudget at $10.7 M.

Construction in the summer of 2021 by BYZ Enterprises
Construction in the summer of 2021 by BYZ Enterprises
Sauder Chute Spillway near completion, February 2022
Sauder Chute Spillway near completion, February 2022
New undershot control gates in place.
New undershot control gates in place.
Replacement of bridge over approach channel
Replacement of bridge over approach channel

Reservoir Projects

Chin Reservoir Expansion and Modernization project

This project will expand Chin reservoir, which is an existing off-stream reservoir on the St. Mary main canal in Section 23 TWP 7-RG 15 – W4M approximately 30 km southeast of the town of Taber. In addition to increasing water storage, an important aspect of the project is modernizing the existing ancillary reservoir structures for aligning with provincial dam safety regulations and increasing the flood handling capacity of the reservoir. This includes construction of a new east dam, replacement of the existing cast in place outlet at the west dam and construction of a new outlet spillway on the east dam. The West dam will also have to be raised and the road over the crest of the dam likewise will also have to be raised.


The reservoir capacity will be increased by raising the height of the existing dams and re-locating the east dam by approximately 10 km, which adds approximately 100,000 acre feet of storage with a flooded area of approximately 1,000 hectares required for the new section.


Increased storage at Chin reservoir will benefit the Raymond and St. Mary River Irrigation Districts with increased water security, which have a joint agreement for management and maintenance costs on the Main canal well as shared ownership of 3 small Hydro power facilities on the St. Mary Main canal.

First nations consultation and environmental assessments are underway, as well as discussions with affected landowners. Engineering and geotechnical studies are being undertaken concurrently. A Historical resource impact study has also been commissioned. The current land use within the reservoir footprint is agriculture, with all land privately owned.

Schedule 

Construction will begin once the design is completed, the land is acquired, all regulatory requirements are met and approvals are received. Completion of the project will take up to four years once construction commences. 

More on the project can be found here: https://smrid.com/projects/chin-expansion/

Cost Estimate 

Preliminary estimate: $132.99 M.

ChinReservoir

Share this Post:

Photograph of WaterPortal Board Member Ross Douglas

Ross Douglas

Board Member

Ross has extensive executive experience in Operations, Governance, Information Technology and Strategy at the board and senior management level including Mancal Corporation, Mancal Energy, Highridge Exploration and Atlantis Resources. He has worked in Oil and Gas, Coal, Commercial Real Estate, Portfolio Management, Recreation, Retail and Water and Wastewater Treatment. His experience is also geographically diverse having overseen operations in Canada, the United States, United Kingdom and Northern Ireland. Additionally, he has been on the board of companies with operations in Argentina, Azerbaijan, Barbados, Kazakhstan, and Russia. He has served on numerous Public, Private and Not for Profit Boards across a number of industries.

Ross has been active on several industry Boards and committees including the Canadian Association of Petroleum Producers (CAPP) and The Schulich School of Engineering Industry Advisory Council at the Schulich School of Engineering.

Photograph of WaterPortal Board Member Brian Mergelas

Brian Mergelas, PhD, ICD.D

Board Member

Brian is a seasoned Cleantech entrepreneur with a proven history of successfully bringing complex water technologies to the market.   With over 25 years of experience, he has led various organizations to achieve significant milestones in the industry. 

Having started as the founding CEO of the Pressure Pipe Inspection Company (PPIC) and later taking the helm at the Water Technology Acceleration Project (WaterTAP), Brian’s entrepreneurial spirit has been instrumental in driving innovation and growth within the sector. 

He is an active investor in the cleantech sector and has served on many boards including the Ontario Clean Water Agency. 

Actively engaged in industry associations like AWWA, WEF, IWA, and ASCE, Brian enjoys collaborating with fellow professionals to promote advancements in the field. 

Brian holds an undergraduate degree and a PhD in Physics from Queen’s University, which has provided him with a solid technical foundation.   As a member of the Institute of Corporate Directors, he brings valuable insights to corporate governance.